Complete mechanical execution designation of “Packaging Material Factory”

PROJECT DESCRIPTION

The client planned to construct new production halls in multiple phases on the site. In the first phase, the main building, which includes production halls, a warehouse, social facilities, and an office block, as well as the hazardous materials storage and the gatehouse, was completed.

Our company undertook the execution of the complete building engineering systems:

– Development of the internal utility network (fire hydrant network, drinking water supply, pressurized and gravity sewage lines, gas lines).
– Installation of the internal drinking water pressurized and sewage drainage network.
– Design of the technological cooling system with the installation of two chillers.
– Development of air handling systems with the installation of two standard and one DX air handling units, along with the establishment of an explosion-proof exhaust network.
– Development of a compressed air network.
– Installation of a heating system with four cascade-connected condensing gas boilers.
– Establishment of central automation.

PROJECT DETAILS

Client
NORDFILM Packaging Kft.
Area
3000 m2

PROJECT IMAGES

Looking for quality execution?

Request a quote NOW!